Size: 1387
Comment:
|
Size: 1393
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 9: | Line 9: |
* NodeSherritt -- need to reschedule an install date | * NodeSherrett -- need to reschedule an install date |
Line 21: | Line 21: |
* Sechzig - backyardShedGW, 2locos, ChimneyOmni | * Sechzig - gateway in backyard shed, 2 locos, chimney omni |
Line 23: | Line 23: |
* NodeSherritt - still need to schedule - maybe on 9/11 | * NodeSherrett - still need to schedule - maybe on 9/11 |
Line 25: | Line 25: |
* Russell Travel - out of town next two weeks, will skip weekly meetings, Board meeting will be September monthly. | * Russell out of town next two weeks, will skip weekly meetings, Board meeting will be at September monthly. |
Location: Jitsi
Date and Time: Wednesday, August 25, 2021, 5:30-8:00 p.m.
Scribe: You
Roll Call: RussellSenior,TomasKuchta,JasonBergstrom,SteveTree
Agenda
- Node notes:
- VZA Homes decommissioning getting organized
NodeSherrett -- need to reschedule an install date
- Russell travel plans
- None Yet
Notes
- Node notes:
- VZA Nodes - Carl wrote up plan for GreenX(mgmt co.) to attend decomms, maybe weekends of Sept. 11th and 18th
- Mgmt co. needs to give tenants 24 hour notice if we need in tenant space or to be on the roof
- Steel - gateway, 2 radios (no need to be on roof)
- Rigler/Wygant - chimney omni, gateway, 2-3 APs, leave enclosure
- Mohawk - gateway, omni on roof, directional radio
- Weidler - 3 APs on roof, office, gateway
- Sechzig - gateway in backyard shed, 2 locos, chimney omni
NodeGriswold - still have an ethernet issue, Ted turned off generic SSIDs on AP
NodeSherrett - still need to schedule - maybe on 9/11
NodeStreetRoots - still need to contact
- VZA Nodes - Carl wrote up plan for GreenX(mgmt co.) to attend decomms, maybe weekends of Sept. 11th and 18th
- Russell out of town next two weeks, will skip weekly meetings, Board meeting will be at September monthly.
- DIN meeting today, change in Federal broadband benfit reduced to $30